# Dar Global's delivery record and Trump Plaza Jeddah

Source: https://www.saudipropertyinvestment.com/en/article/trump-plaza-jeddah-developer-track-record-delivery
Updated: 2026-11-16
Publisher: Saudi Property Investment (Omnia Capital Group)

## The short answer

Dar Global, the London-listed arm of Dar Al Arkan, has completed four projects, all outside Saudi Arabia: two towers in Dubai, including DaVinci Tower by Pagani, and two schemes in London. None of its six Saudi projects is finished yet; the first, Neptune in Riyadh, is due in Q4 2027. Trump Plaza Jeddah, launched in January 2026, is scheduled for Q4 2030, with Al Dahlawi as main contractor for the Amaya district around it.

## Key points

- Dar Global's 2025 results list four completed projects, all outside Saudi Arabia: a 467-unit tower on the Dubai Canal and DaVinci Tower by Pagani in Dubai, and Oh So Close and The Mulliner in London.
- Its six Saudi projects are all under construction, from Neptune in Riyadh, due in Q4 2027, to Trump Plaza Jeddah, Padel Living Residences and Rayana, due in Q4 2030.
- Its parent, Dar Al Arkan, was founded in Riyadh in 1994, listed on the Saudi Exchange in 2007 and moved its development operations to Dar Global in 2024.
- Main contractors are appointed for both Trump projects in Jeddah: Arabian Construction Company for Trump Tower Jeddah, Al Dahlawi for Amaya, where Trump Plaza sits.
- At 30 June 2026 Dar Global held US$616.3 million of restricted escrow cash across its markets; in Saudi Arabia, buyers' payments go into each project's escrow account under Wafi.

## Dar Global's delivery record: what its accounts show

Trump Plaza Jeddah is developed by Dar Global, the international arm of Dar Al Arkan, listed on the London Stock Exchange under the ticker DAR. [Dar Al Arkan](https://www.daralarkan.com/en/about-us), founded in Riyadh in 1994 and listed on the Saudi Exchange in 2007, is its controlling shareholder, and in 2024 it moved its development operations to Dar Global. Dar Global now builds the group's new projects in the Kingdom.

Because Dar Global is listed, its results are public, with a status table for every project. Its [2025 results](https://www.ticker.app/lse/DAR/rns/2026-03-11/Full-Year-Results/1301W), published on 11 March 2026, and its [half-year results](https://es.tradingview.com/news/reuters.com,2026-09-24:newsml_RSX0581Wa:0-reg-dar-global-plc-dar-global-half-year-2026-results/), published in September 2026, are the best guide to what it has delivered and when it expects to deliver the rest.

## What Dar Global has completed

| Project | Place | Units | Launched |
|---|---|---|---|
| A residential tower on the Dubai Canal | Dubai | 467 | Q3 2021 |
| DaVinci Tower by Pagani | Dubai | 85 | Q1 2022 |
| Oh So Close | West Ealing, London | 17 | Q2 2023 |
| The Mulliner, 149 Old Park Lane | London | 1 | Q2 2022 |

All four are outside Saudi Arabia, and three of the four have fewer than 100 units. Dar Al Arkan's own record in the Kingdom is longer: Ishbiliyah and Al Munsiya in Riyadh and Al Noor Villas in Madinah from 2003, Al Qasr in Riyadh from 2005 and Qasr Mall, opened in 2013. That record belongs to the parent, not to Dar Global.

## What it is building in Saudi Arabia

Dar Global's half-year results of September 2026 list six Saudi projects, all under construction:

| Project | City | Launched | Units | Scheduled completion |
|---|---|---|---|---|
| [Neptune Interiors by Mouawad](https://www.saudipropertyinvestment.com/en/developments/riyadh/neptune-interiors-mouawad-villas-riyadh) | Riyadh | Q4 2024 | 200 | Q4 2027 |
| [Amaya](https://www.saudipropertyinvestment.com/en/developments/jeddah/amaya-jeddah) | Jeddah | Q1 2026 | 523 plots | Q1 2029 |
| [Trump Tower Jeddah](https://www.saudipropertyinvestment.com/en/developments/jeddah/trump-towers-jeddah) | Jeddah | Q4 2024 | 561 | Q4 2029 |
| [Trump Plaza Jeddah](https://www.saudipropertyinvestment.com/en/developments/jeddah/trump-plaza-jeddah) | Jeddah | Q1 2026 | 516 | Q4 2030 |
| [Padel Living Residences](https://www.saudipropertyinvestment.com/en/developments/jeddah/padel-living-residences-jeddah) | Jeddah | Q2 2026 | 452 | Q4 2030 |
| [Rayana, Wadi Safar](https://www.saudipropertyinvestment.com/en/developments/riyadh/rayana-wadi-safar) | Riyadh | Q1 2026 | 139 | Q4 2030 |

Neptune, its first launch in the Kingdom, will be the first test of its delivery here. The Amaya date refers to the district's plots; the homes inside it carry their own dates.

## What has happened since December 2025

**Trump Tower Jeddah reached its main contract.** Launched in December 2024, it entered pre-construction by May 2025, its enabling works were completed by Specialised Italian Foundation Company, and Arabian Construction Company [won the main contract](https://www.meed.com/arabian-construction-company-wins-trump-tower-jeddah) in November 2025: about eleven months from launch to main contract.

**Amaya and Trump Plaza followed.** Trump Plaza was launched in January 2026, and in April Dar Global [appointed Al Dahlawi Company for Contracting](https://www.tradearabia.com/News/461537/Dar-Global-appoints-Al-Dahlawi-as-main-contractor-for-Amaya-Jeddah/CONS) to deliver key phases of Amaya, including its residential neighbourhoods: about three months from launch to main contractor.

**Rayana's infrastructure was let.** The half-year release reports a SAR 338 million infrastructure contract for Rayana at Wadi Safar, awarded to Compass and Bin Omairah Company.

**Revenue followed construction.** Dar Global's [half-year release](http://www.prnewswire.com/news-releases/dar-global-delivers-66-revenue-growth-in-hy-2026-as-portfolio-gdv-reaches-us23bn-302894225.html) reported revenue up 66%, driven by revenue recognised on projects including Neptune, and cumulative contracted sales of US$3.9 billion across 4,380 units. At 30 June 2026 it held restricted escrow cash of US$616.3 million across its markets, including retentions of US$45.6 million.

**The dates held.** Between the 2025 results and the half-year results, the scheduled completion of each Saudi project listed in both stayed the same.

## How off-plan sales in Saudi Arabia protect a buyer

Off-plan homes in the Kingdom are sold under licence through [Wafi](https://www.saudipropertyinvestment.com/en/glossary/wafi), the Real Estate General Authority's off-plan platform. A developer must hold an escrow account agreement with a licensed bank. While a project holds only a marketing licence, a reservation is capped at 5% of the unit's value and goes into escrow. The sale contract must state the handover date by day. Our guide to [buying off-plan](https://www.saudipropertyinvestment.com/en/guides/off-plan-property-saudi-arabia) sets out what happens if a project is late.

## What the record means for Saudi and non-Saudi buyers

**The case for Dar Global** is that it is a listed company with public accounts and published project dates, a parent with three decades of building in the Kingdom, completed towers in Dubai, and appointed main contractors on both its Jeddah Trump projects.

**The case for caution** is that its Saudi record is new and Trump Plaza is a long commitment. You pay 90% of the price before handover, scheduled for Q4 2030, and Neptune will not show how Dar Global hands over in the Kingdom until late 2027.

**What to watch over the next year.** Three signals will tell you more than any brochure: whether Neptune's Q4 2027 date holds in each set of results until handover; whether Trump Tower Jeddah, the first Jeddah project to reach a main contract, keeps its Q4 2029 date; and whether the dates for Amaya's buildings move. In 2026 Dar Global published its full-year results in March and its half-year results in September, so you can check each date twice a year.

The weighing is the same for Saudi and non-Saudi buyers. A non-Saudi buyer has one more step: confirming that the plot is inside a designated zone, which our article on [foreign ownership at Trump Plaza Jeddah](https://www.saudipropertyinvestment.com/en/article/foreign-ownership-trump-plaza-jeddah) explains. The brand deal itself is covered in our article on [the Trump Organization and Trump Plaza](https://www.saudipropertyinvestment.com/en/article/trump-organisation-saudi-trump-plaza-jeddah).

## What a buyer should do now

Before you reserve, ask for:

- the Wafi licence number and the escrow account named in the contract, and check both;
- the handover date by day, the remedies for delay and any long-stop date in the sale agreement;
- what the agreement says if the Trump licence ends;
- the developer's latest programme for your building, set against the date in its last published results.

Our profile of [Dar Global](https://www.saudipropertyinvestment.com/en/developers/dar-global) is updated as projects progress, and the [payment plan calculator](https://www.saudipropertyinvestment.com/en/tools/payment-plan-calculator) shows how much you will have paid at each stage.

## Questions

### Has Dar Global completed any projects?

Yes, outside Saudi Arabia. Its 2025 results list four completed projects: a 467-unit tower on the Dubai Canal; DaVinci Tower by Pagani in Dubai, with 85 units; and Oh So Close in West Ealing and The Mulliner on Old Park Lane in London. Its Saudi projects are all still being built.

### When will Trump Plaza Jeddah be completed?

Dar Global schedules it for Q4 2030, in both its 2025 results and its half-year results of September 2026. Al Dahlawi has been main contractor for the surrounding Amaya district since April 2026. The binding date is the one in your sale agreement, set by day under the off-plan rules.

### Is Dar Global a reliable developer?

It is a listed company that publishes audited accounts and a status table for every project, and its parent has built in the Kingdom since 1994. Its own Saudi record is still new: no Saudi project is finished, and Neptune in Riyadh, due in Q4 2027, will be the first. Judge it on progress against those published dates.

### How is Dar Global related to Dar Al Arkan?

Dar Al Arkan, founded in Riyadh in 1994 and listed on the Saudi Exchange since 2007, set up Dar Global for its international projects and is its controlling shareholder. In 2024 Dar Al Arkan moved its development operations to Dar Global, which is listed on the London Stock Exchange under the ticker DAR.

### How are my payments protected when I buy off-plan from Dar Global?

Off-plan sales in Saudi Arabia need a licence through Wafi, the Real Estate General Authority's off-plan platform, and every payment goes into an escrow account for that project at a licensed bank. Before a sale licence, a reservation is capped at 5% of the unit's value. Pay only into the account named in your contract.

## Sources

- [Dar Global plc: full year results 2025, completed projects and project status table (11 March 2026), checked 16 November 2026](https://www.ticker.app/lse/DAR/rns/2026-03-11/Full-Year-Results/1301W)
- [Dar Global plc: half year results 2026, project status table and escrow (September 2026), checked 16 November 2026](https://es.tradingview.com/news/reuters.com,2026-09-24:newsml_RSX0581Wa:0-reg-dar-global-plc-dar-global-half-year-2026-results/)
- [Dar Global: 66% revenue growth in HY 2026 as portfolio GDV reaches US$23bn (30 September 2026), checked 16 November 2026](http://www.prnewswire.com/news-releases/dar-global-delivers-66-revenue-growth-in-hy-2026-as-portfolio-gdv-reaches-us23bn-302894225.html)
- [Dar Al Arkan: about us, history and the move of development operations to Dar Global, checked 16 November 2026](https://www.daralarkan.com/en/about-us)
- [MEED: Arabian Construction Company wins Trump Tower Jeddah (26 November 2025), checked 16 November 2026](https://www.meed.com/arabian-construction-company-wins-trump-tower-jeddah)
- [Arab News: Jeddah set for $1bn Trump Plaza, pre-construction on Trump Tower Jeddah (29 September 2025), checked 16 November 2026](https://www.arabnews.pk/node/2617177/business-economy)
- [TradeArabia: Dar Global appoints Al Dahlawi as main contractor for Amaya, Jeddah (23 April 2026), checked 16 November 2026](https://www.tradearabia.com/News/461537/Dar-Global-appoints-Al-Dahlawi-as-main-contractor-for-Amaya-Jeddah/CONS)
- [Real Estate General Authority: Wafi, off-plan sales and leasing, checked 16 November 2026](https://rega.gov.sa/en/rega-services/platforms/wafi-off-plan-sales-and-lease/)